Hitachi Zosen Receives Order for Construction and Operation of Energy-from-Waste Plant from Abiko City, Chiba
Feb 17, 2020
Hitachi Zosen Corporation has received an order for the construction and operation of an Energy-from-Waste plant from Abiko City, Chiba (Mayor: Junichiro Hoshino).
In this project, Abiko City will establish a stable and safe waste treatment system in the future and embody the "New Clean Center Development Basic Policy" set forth in the "Detailed Plan for the Development of New Waste Treatment Facilities", which has been planned so that an energy recovery type waste treatment facility is established for proper operation and build a recycling-oriented society.
Our Company undertakes the project in procurement, engineering and construction (EPC). And, following completion, the facility will be operated by Abiko Environment Technology Co. Ltd., special purpose company established by our group for 20 years.
Outline
1.Client | Abiko City, Chiba (Mayor: Junichiro Hoshino) |
---|---|
2.Project | Abiko City New Waste Treatment Facility Development and Operation Project |
3.Contract | DBO (Design-Build-Operate) |
4.Period | Design and Construction till March 2023 Operation and Maintenance April 2021-March 2041(20 years) |
5.Capacity | Stoker-type incinerator 120t/day (60t/day x 2units) with power generator (Planed processing volume:27,206= t/year) |
6.Location | 2264 and 2274, Nakabyo, Abiko-city, Chiba |
7.Contract amount | JPY 17,800 million (excluding tax) |
8.Consortium | Representative Hitachi Zosen Corporation Tokyo Head Office Members Rinkai Nissan Construction Co., Ltd. Chiba Office, Hitz Environment Service Co., Ltd. Partners Kamimura Corporation, Noda Denki Co., Ltd., Ichikawa Kankyo Engineering Co., Ltd. |
Our Company will actively contribute to achieving the SDGs (Sustainable Development Goals) adopted by the United Nations and solving the global environmental problems by promoting Energy-from-Waste plant solution.